Timeline: From site analysis to stadium opening

February 2012

Cushman & Wakefield site analysis reports completed 


December 2012

Tor di Valle site selected out of 80+ possible locations 


January 2013

Veteran stadium architect, Dan Meis, brought on to lead design 
efforts 


April 2013

Initial Stadio della Roma and Master Site designs completed 


December 2013

Stadio della Roma team presents project vision and scope to 
Mayor Marino 


March 2014

Public unveiling of the stadium model at Comune di Roma 


December 2014

Assemble Capitolina recognized Stadio della Roma as a project of public interest for the City of Rome

April 2015

Geotechnical analysis begins on-site


June 15, 2015

Initial site dossier submission to Rome City Council 


April 29, 2016

Stadio della Roma technical designs submitted to CONI 


May 30, 2016

Mastersite Supplementary technical dossier submitted to COMUNE